April - May 2025 Updates:

MEP testing and commissioning are ongoing.

Consultant snagging has reached Level 65.

Guest room furniture installation has progressed to Level 58, with over 45% completed.

The contractor is installing the building façade lighting.

Lobby fit-out works have progressed to 65% completion.

Fit-out works for All-Day Dining on Level 13 have reached 50%.

Fit-out works for All-Day Dining on Level 14 have reached 35%.

Leisure deck fit-out on Level 11 has commenced, with 40% progress achieved.

Fit-out contractors for Levels 15 and 61 (offices and meeting rooms) have been appointed, and works have commenced.

The First Group Commercial Team is finalizing the appointment of the gym fit-out contractor.

Fit-out for the ground floor promenade lobby has commenced, with 10% progress achieved.

The First Group project and hotel operator teams are conducting regular workshops to address feedback.