Progress Updates

February - March 2025 Updates:

MEP testing and commissioning are ongoing.

Consultant snagging has reached Level 39.

Guest room furniture installation has progressed to Level 34.

The contractor is installing the building façade lighting.

Lobby fit-out works have commenced, with 20% progress achieved.

Fit-out works for the All-Day Dining and the Level 14 restaurant are underway.

The Level 11 leisure deck fit-out contractor has been appointed.

Negotiations for the GF promenade lobby fit-out contractor are in the final stages.

The First Group project and hotel operator teams are conducting regular workshops to address feedback.

The interior design team is collaborating with the hotel operator to develop interiors for:

Level 61 – Gym and spa

Level 15 – Offices and meeting rooms

Level 16 – VIP lounge and kids’ play area