The First Collection at JVC
Welcome to The First Collection at Jumeirah Village Circle, a Tribute Portfolio Hotel. As the first member of Marriott Bonvoy's Tribute Portfolio in the Middle East, the four-star lifestyle property marks a significant milestone for the region while setting a new benchmark for quality and affordability in Dubai’s upper-midscale hotel market.
The modern 40-storey tower was the first hotel to debut under The First Group’s lifestyle hospitality brand, The First Collection. With 491 beautifully appointed suites and premium amenities, including a stylish business lounge, expansive swimming pool and sundeck, fully equipped gym, and spa services with separate male and female treatment facilities, it offers an exceptional guest experience.
Situated in the vibrant district of Jumeirah Village Circle, the hotel’s central location places it near the city’s top business precincts and leisure attractions. Adjacent to three main roads, it’s only a 20-minute drive from Dubai’s beaches, Downtown Dubai, Dubai South, and Al Maktoum International Airport, which will become the world’s largest international air hub.
Prior to opening, The First Collection at JVC received major industry awards, sowing the seeds for its long-term success. At the 2020-21 Arabian Property Awards, the hotel won Best New Hotel Construction & Design, Best Hotel Architecture, and Best Hotel Interior. It was also named Hotel of the Future at the ID Design Awards and Leisure and Hospitality Project of the Year at the prestigious Middle East Architect Awards.
TRIPADVISOR’S TRAVELERS’ CHOICE AWARDS 2022
The First Collection at JVC is among the winners of TripAdvisor's Travellers Choice Awards for Hottest New Hotel 2022
AWARD WINNER
Best Hotel Architecture in Dubai, New Hotel Construction & Design, Hotel Interior
The First Collection at JVC
Perfectly situated in Jumeirah Village, The First Collection at Jumeirah Village Circle offers investors a fantastic opportunity to capitalise on the precinct's incredible growth.
Take a look inside the property and learn why it is a top hotel investment option.
FACILITIES
24-hour Reception
24/7 reception and concierge services
Valet Parking
Complimentary valet parking service
Business Lounge
Modern, high-tech facilities for business guests
Laundry service
24/7 laundry service
Wi-Fi
Complimentary high-speed internet access
World-class Dining Facilities
A fine selection of restaurants, cafes and bars
Swimming pool
Stunning rooftop swimming pool and sundeck
Gymnasium
Fully-equipped fitness centre
Satellite Television
Local and international digital channels
Booking Facilities
Tour and leisure activity booking services
Gallery
Project Development Progress
Progress Updates
Our consultant NORR has completed 50% of the detailed design and will complete 100% of the design by the mid of August 2015.
The preliminary design has been approved by Nakheel and Trakhees.
The mobilization permit required for Zetas the shoring and piling contractor of the project was obtained on 17th of June, 2015.
The contractor has commenced with the mobilization activities at the site.
The shoring permit is expected to be issued by the 16th of July, 2015.
VIP lounge and guest rooms’ initial designs which have been completed by our interior design consultant HBA have been approved by the hotel operator. The detailed drawings for the same are under preparation by the consultant.
All room’ types’ furniture layouts have been approved by the operator. The detailed drawings for the same are under preparation by the consultant.
All room color schemes and finishes which have been prepared by the Interior Design consultant HBA have been approved by the operator. The detailed drawings for the same are under preparation by the consultant.
The operator has approved the initial operation layout for the commercial kitchen which was prepared by the kitchen’s consultant.
HBA has submitted the first sketches of F&B areas for the operator review to ensure that they are designed in the most efficient and operational way.
Progress Updates
Our consultant NORR has completed 75% of the detailed design and will complete 100% of the design by the middle of August 2015.
The preliminary design has been approved by Nakheel and Trakhees.
The shoring permit was obtained on the 20th of July, 2015.
Zetas, the shoring and piling contractor of the project has commenced with the works on site. 70 Meters of the guiding walls which are part of the shoring works have been completed.
The detailed interior design drawings of the approved VIP Lounge and VIP guest’ room’s designs have been prepared by the consultant.
The detailed interior design drawings of all room’ types which has been approved by the operator have been prepared by HBA, the consultant.
All room color schemes and finishes which have been prepared by the Interior Design consultant HBA have been approved by the operator. The detailed drawings for the same are under preparation by the consultant.
The commercial kitchen consultant is preparing the detailed drawings for final review.
The project interior design consultant is modifying the first sketches of F&B areas based on the comments received from the operator.
Progress Updates
Our consultant NORR has completed 100% of the detailed design.
Zetas, the shoring and piling contractor has completed 50% of the shoring works.
The detailed interior design drawings of the approved VIP Lounge and VIP guest’ room’s designs have been prepared by the consultant and submitted to the operator for their review and comments.
HBA the interior design consultant has issued the operator approved detailed interior design drawings of all room’ types to the project’s architect, Norr.
All room color schemes and finishes which have been prepared by the Interior Design consultant HBA have been approved by the operator. The detailed drawings for the same have been prepared by the project’s architect.
The commercial kitchen consultant is preparing the detailed drawings for final review.
The project interior design consultant has modified the first sketches of F&B areas based on the comments received from the operator and resubmitted the same drawings for the operator final review and approval.
Progress Updates
Our consultant NORR is planning to make his submission for obtaining the final design approval to the authorities by the 15th of October, 2015.
Zetas, the shoring and piling contractor has completed 65% of the shoring works and their work is ongoing.
The detailed interior design drawings of the approved VIP Lounge and VIP guest room’s designs have been prepared by the consultant and submitted to the operator for their review and comments.
HBA the interior design consultant has completed the design of the All Day Dining restaurant and the Roof Top Restaurant/ Bar for our review and comments.
HBA is working on the design of the following areas:
The business centre.
The main lobby.
The GYM and SPA
The commercial kitchen consultant has prepared 50% of the detailed drawings.
The workshop session is ongoing between the project interior design consultant, the operator and The First Group interior design team for the review of the F&B areas based on the comments received from the operator.
Progress Updates
The detailed interior design drawings of the approved VIP Lounge and VIP guest room’s designs which have been prepared by the consultant have been approved by the operator.
HBA the interior design consultant has received our comments on the design of the Roof Top Restaurant/ Bar.
The All Dinning restaurant design presentation has been approved by the operator.
HBA is working on the design of the following areas: The business centre, The main lobby, The GYM and SPA.
The commercial kitchen consultant is working on preparing the detailed drawings.
The workshop session is ongoing between the project interior design consultant, the operator and The First Group interior design team for the review of the F&B areas based on the comments received from the operator.
Progress Updates
Norr the lead consultant of the project has made the submission for obtaining the final design approval to the authorities on the 15th of October, 2015. Comments were received and Norr is attending to these comments and the resubmission of the drawings will happen around the 8th of December, 2015.
Zetas, the shoring and piling contractor has completed 95% of the shoring works and their work is ongoing.
The piling design permit has been issued on the 30th of November, 2015. Zetas will commence with the piling works after the completion of the shoring and excavation’s works.
The piling work will be completed in 40 days.
The main building tender package has been released to grade A contractors for biding on the construction of the hotel. The last date for receiving the bids is the 13th of December, 2015.
Approval of the concept design for those areas including the preparation of the MEP layouts for all the rooms.
HBA the project’s interior design consultant is working on the design of the Roof Top Restaurant/ Bar based on our comments issued to them earlier.
HBA is still working on the design of the following areas: The business center, The main lobby, The GYM and SPA.
Progress Updates
Norr the lead consultant of the project has made the re submission of the final design approval to the authorities based on the previous comments received.
Zetas, the shoring and piling contractor has been completed the shoring works.
Zetas has commenced with the piling works. This work is expected to be completed by the 15th of Feb, 2016.
The bids for the main building tender package have been received from the grade A contractors who have participated; the technical and commercial evaluations of the submitted bids are now being jointly carried out by The First Group’s construction team and the projects’ consultant.
HBA the project’s interior design consultant has completed the design of the Roof Top Restaurant/ Bar based on the comments from the operator and our comments. The updated design has been issued to the operator for their final review and sign off.
HBA is still working on the design of the following areas: The business center, The main lobby, The main lobby
Progress Updates
Zetas has commenced with the piling works. This work is expected to be completed by the end of Feb, 2016.
The announcement of the main building contractor will be during the last week of February, 2016.
The operator has approved the design of The Roof Top restaurant based on our interior design consultant’s (HBA) design.
HBA have submitted the design of the business center area to the operator for their review.
HBA is still working on the design of the following areas: The main lobby and the GYM and SPA
Progress Updates
Zetas the shoring and piling contractor will commence with the dewatering work during the first week of March, 2016.
A few days after the commencement of the dewatering the excavation around the piles will start and the piles’ testing will follow. After the completion of the pile testing the site will be handed over to the appointed main building contractor. This is expected to be during the first week of April, 2016. At this point the main building contractor will commence with his mobilization to the site and construction works
The main building contractor has been appointed.
All public areas, main lobby and GYM designs have been reviewed by the operator some comments were highlighted which are being dealt with.
Façade lighting design is under progress.
The rooms and common area’s finishing schedules have been issued by HBA the interior design consultant of the project.
Progress Updates
Zetas the piling contractor has commenced with the dewatering work.
The excavation work shall be completed by the 15th of April, 2016.
The piles’ testing has started and it is expected to be completed during the first week of April, 2016.
The main building contractor has commenced with the mobilization to the site.
Based on the operator’s comments The First Group Interior Design team has produced the revised design drawings for all public areas, main lobby and GYM for their final approval.
Façade lighting design is under progress.
Progress Updates
Zetas the shoring and piling contractor has completed his work and has handed over the site to the main building contractor.
The excavation work has been completed.
The piles’ testing has been completed.
The main building contractor has completed their mobilization to the site and have commenced.
The operator has approved the design of the public areas, main lobby and GYM.
The concept Façade lighting design has been presented by the lighting consultant and it is under review.
Progress Updates
The main building contractor have completed their mobilization to the site and commenced with the piles’ breaking.
The piles’ breaking will be completed on the 15th of June, 2016.
The concrete pouring for the lifts’ pit is planned to take a place within 10 days and the main raft concrete pouring is expected to happen during the 1st week of August, 2016.
The detailed interior design drawings of the main lobby, the GYM and the SPA which have been prepared by the project’s interior design consultant Studio HBA have been approved by the operator.
The commercial kitchen consultant has prepared the detailed drawings and had them approved by the operator.
The workshop sessions are ongoing between Studio HBA, the operator and The First Group interior design team, for the review of the F&B areas based on the comments received from the operator.
Progress Updates
The piles’ breaking has been completed.
The concrete pouring for the lifts’ pit has been completed.
The excavation and preparation works for the casting of the raft foundation are ongoing.
The main raft concrete pouring is expected to happen during the 1st week of August, 2016.
The interior designs of the hotel’s rooms, suites, common areas, main lobby, restaurants and BOH areas have been all approved by the operator.
All the above mentioned approved designs have been passed on to the contractor for execution.
Progress Updates
The excavation and preparation works for the casting of the raft foundation is 95% complete.
The main raft concrete pouring is expected to happen during the 2nd week of August, 2016.
The interior designs of the hotel’s rooms, suites, common areas, main lobby, restaurants and BOH areas have been all approved by the operator.
All the above mentioned approved designs have been passed on to the contractor for execution.
Progress Updates
Based on the final approval obtained on the design drawings from the operator, the main contractor start to source all agreed finishes for our final review and selection.
All public areas designs have been completed and reviewed by Wyndham with comments.
Façade lighting design is completed and the same has been submitted as final to the consultant.
BOH revised design has been issued to the consultant.
Progress Updates
Based on the final approval obtained on the design drawings from the operator, the main contractor is sourcing all agreed finishes for our final review and selection.
SHBA the project’s interior designer consultant has completed the operator’s comments on all of the public areas.
Progress Updates
SHBA the project’s interior designer consultant and The First Group interior design team are working together to finalize the selection of the finishes materials which will be used in the mock-up room for the operator to review and sign off.
Progress Updates
The First Group’s interior design team has selected the finishes materials which will be used in the mock-up room; waiting for the operator review and sign off.
Progress Updates
Podium 3 (P3 level) slab has been completed.
Podium 4 (P4 level) slab will be cast on the 8th of January, 2017.
The contractor is planning to commence with the block work in the basement by the 15th of January, 2017.
Progress Updates
Podium 4 (P4 level) slab has been completed.
The next slab (the first typical floor slab) will be cast on the 7th of February, 2017.
The contractor is planning to commence with the block work in the basement by the 15th of February, 2017.
Progress Updates
T1& T2 the first and second typical slabs have been completed.
T03 slab will be cast on the 7th of March, 2017.
The contractor has already commenced with the block work in the basement.
The First Group interior design team is getting all the designs ready for the preparation of the show flat at the site.
All the tiles selection for the standard and VIP rooms have been finalized and ordered.
All the sanitary ware and mixers for the standard and VIP rooms has been finalized and ordered.
Progress Updates
T04 the forth typical slabs has been completed.
T05 slab will be cast on the 8th of April, 2017.
The contractor has already commenced with the block work in the basement.
The First Group interior design team has completed the all the designs required for the preparation of the show flat at the site and handed them over to the contractor for their execution.
Progress Updates
T09 the 9th typical slab has been completed.
T10 slab will be cast on the 5th of May, 2017.
The contractor has already commenced with the block work in the basement and the ground floor.
The First Group interior design team has completed the all the designs required for the preparation of the show flat at the site and handed them over to the contractor for their execution.
Progress Updates
T14, the 14th typical slab, has been completed.
T15 slab will be cast on the 5th of June, 2017.
The contractor has already commenced with the block work in the basement and the ground floor.
The First Group interior design team is working along with the contractor on getting the show flat at the site ready by the end of June, 2017.
Progress Updates
T18, the 18th typical slab, has been completed.
T19 slab will be cast on the 5th of July, 2017.
The contractor has already commenced with the block work in the basement, the ground floor and the podium floors.
The First Group interior design team is working on the final touches for preparing the show flat at the site ready. It should be completed during the second week of July, 2017.
Progress Updates
T22, the 22nd typical slab, has been completed.
T23 slab will be cast on the 4th of August, 2017.
The contractor has already commenced with the block work up to the 4th floor.
The curtain wall contractor has been appointed.
The show flat at the site is almost ready. Final wall painting is ongoing. The furniture will be delivered by the middle of September, 2017.
Progress Updates
T29, the 29th typical slab, has been completed.
T30 slab will be cast on the 2nd of September, 2017.
The contractor has already commenced with the block work up to the 7th floor.
The curtain wall contractor has prepared the façade shop drawings and submitted them to the consultant for their review and approval.
The show flat at the site has been completed. The furniture will be delivered by the middle of September, 2017.
Progress Updates
T33, the 33rd typical slab, has been completed.
T34 slab will be cast on the 3rd of October, 2017.
The block work is on progress up to the 9th floor.
The curtain wall contractor will commence with the frame works by the 15th of October, 2017.
Progress Updates
T38, the 38th typical slab, has been completed.
T39 slab will be cast on the 4th of November, 2017.
The block work is on progress up to the 9th floor.
The curtain wall contractor has commenced with the framing works.
Progress Updates
The superstructure has been completed.
The block work is on progress up to the 17th floor.
The curtain wall contractor is fixing the façade glass brackets.
Progress Updates
Block work is complete up to the 38th floor and it is ongoing on the 39th and the 40th floors.
Wall painting is ongoing up to 27th floor.
Wall tiling work is complete up to the 10th floor and ongoing on the 11th &12th floors.
Floor tiling work is ongoing on the 4th floor.
Curtain wall contractor has commenced with the glass production and installation.
Progress Updates
Block work is complete up to the 40th floor and it is ongoing on the 41st and the 42nd floors.
Wall painting is ongoing up to 29th floor.
Wall tiling work is complete up to the 12th floor and ongoing on the 13th &14th floors.
Floor tiling work is ongoing on the 4th and the 5th floors.
Curtain wall contractor has commenced with the glass production and installation.
Progress Updates
Block work is complete up to the 41st floor and it is ongoing on the 42nd floor
Wall painting is ongoing up to 31st floor.
Wall tiling work is complete up to the 13th floor and ongoing on the 14th &15th floors.
Floor tiling work is ongoing on the 5th and the 6th floors.
Curtain wall work is ongoing.
Progress Updates
Block work is complete up to the 42nd floor and it is ongoing on the 43rd floor.
Wall painting is ongoing up to 33rd floor.
Wall tiling work is complete up to the 15th floor and ongoing on the 16th &17th floors.
Floor tiling work is ongoing on the 6th and the 7th floors.
Curtain wall work is ongoing.
The fit out work for the F&B outlets will commence in April, 2018.
Progress Updates
Block work is complete up to the 43rd floor and it is ongoing on the 44th floor
Wall painting is ongoing up to 35th floor.
Wall tiling work is complete up to the 16th floor and ongoing on the 17th &18th floors.
Floor tiling work is ongoing on the 7th and the 8th floors.
Curtain wall work is ongoing.
The fit out work for the F&B outlets has commenced.
Progress Updates
Block work is complete up to the 44rd floor and it is ongoing on the roof floor
Wall painting is ongoing up to 37th floor.
Wall tiling work is complete up to the 17th floor and ongoing on the 18th &19th floors.
Floor tiling work is ongoing on the 8th and the 9th floors.
Curtain wall work is ongoing.
The fit-out work for the F&B outlets has commenced.
Progress Updates
Wall painting is ongoing up to 39th floor.
Wall tiling work is complete up to the 19th floor and ongoing on the 20th &21st floors.
Floor tiling work is ongoing on the 9th, 10th and 11th floors.
Curtain wall work is ongoing.
The fit-out work for the F&B outlets is ongoing.
Progress Updates
Wall painting is ongoing up to 41st floor.
Wall tiling work is complete up to the 20th floor and ongoing on the 21st & 22nd floors.
Floor tiling work is ongoing on the 11th &12th floors.
Curtain wall work is ongoing.
The fit-out work for the F&B outlets is ongoing.
Progress Updates
Wall painting is ongoing up to the 41st floor.
Wall tiling work is complete up to the 21st floor and ongoing on the 22nd & 23rd floors.
Floor tiling work is ongoing on the 12th &13th floors.
Curtain wall work is ongoing.
The fit-out work for the F&B outlets is ongoing.
Progress Updates
Wall painting is ongoing up to the 41st floor.
Wall tiling work is complete up to the 23rd floor and ongoing on the 24th floor.
Floor tiling work is ongoing on the 14th &15th floors.
Curtain wall work is ongoing.
The fit-out work for the F&B outlets is ongoing.
Progress Updates
Second coat of the wall painting is ongoing up to the 10th floor.
Wall tiling work is complete up to the 25th floor and ongoing on the 26th floor.
Floor tiling work is ongoing on the 15th &16th floors.
Curtain wall work is ongoing.
The fit-out work for the F&B outlets is ongoing.
Progress Updates
Second coat of the wall painting is ongoing up to the 22nd floor.
Wall tiling work for guest rooms is complete up to the 39th floor
Floor tiling work for guestrooms is complete up to 39th floor
Curtain wall work is ongoing.
The fit-out work for the F&B outlets is ongoing.
Progress Updates
Lift lobby marble has been installed up to the 39th floor.
Wall tiling work for guest rooms is complete up to the 39th floor
Floor tiling work for guestrooms is complete up to the 39th floor
Curtain wall work is ongoing.
The fit-out work for all F&B outlets is ongoing.
Progress Updates
Lift lobby marble has been installed up to the 42nd floor.
Wall tiling work for guest rooms is complete up to the 41st floor
Floor tiling work for guestrooms is complete up to the 41st floor
Curtain wall work is ongoing.
The fit-out work for all F&B outlets is ongoing.
Progress Updates
Lift lobby marble has been installed up to the 44th floor.
Wall tiling work for guest rooms is in progress up to the 42nd floor
Floor tiling work for guestrooms is in progress up to the 42nd floor
Curtain wall work is ongoing.
The fit-out work for all F&B outlets is ongoing.
Progress Updates
Wall tiling work for guest rooms is in progress up to the 43rd floor
Floor tiling work for guestrooms is in progress up to the 43rd floor
Curtain wall work is ongoing
The fit-out work for all the F&B outlets is ongoing
Progress Updates
Wall tiling work for guest rooms is in progress up to the 44th floor
Floor tiling work for guestrooms has been completed.
Final curtain wall work is ongoing.
The fit-out work for all the F&B outlets is ongoing.
Super structure, blockwork, and plaster are 100% complete with MEP at 97% complete and aluminum work at 93% complete.
Progress Updates
Wall tiling work for guest rooms has been completed.
Final curtain wall work is ongoing.
The fit-out work for all the F&B outlets is ongoing.
Progress Updates
Final curtain wall work is ongoing.
The fit-out work for all the F&B outlets is ongoing.
Progress Updates
The curtain wall work has been completed.
All the civil and the internal finishes work inside the building have been completed.
Dubai electricity and water authority (DEWA) have inspected the building. The permanent electrical and water connections of the building are expected by 16/09/2019.
Dubai Civil Defense inspection is scheduled on 18/09/2019. Dubai municipality completion certificate of the building is expected to be issued during the 1st week of October, 2019.
The fit-out work for all the F&B outlets is ongoing.
Progress Updates
Dubai Civil Defense authority has carried out their 1st inspection of the building. Minor comments were highlighted during the inspection which will be completed in two weeks by the contractor.
Dubai electricity and water authority (DEWA) has made their final inspection of the building and confirmed the building’s conformity to receive the permanent electrical and water supply. This is expected by to happen before the end of October 2019.
The fit-out work for all the F&B outlets is ongoing.
Progress Updates
The contractor has completed the minor comments which were noted during Civil Defense’s 1st inspection of the building. The 2nd inspection will take place during the 1st week of November 2019. Once completed satisfactory, the Civil Defense certificate will be issued.
The contractor will apply for the permanent electrical and water supply after the receiving the Civil Defense certificate.
The fit-out work for all the F&B outlets is ongoing.
Progress Updates
Dubai Civil Defense certificate has been issued.
The contractor has applied for the building completion certificate. The authority inspection of the building is expected during the second week of December 2019.
The building has already been connected with the permanent electricity and water.
The fit-out work for all the F&B outlets is ongoing.
Progress Updates
The authority has completed the first inspection of the building as part of the completion certificate issuance process. The contractor has noted the minor comments addressed during the inspection and started attending to it immediately.
The furniture supplier has manufactured 40% of the guest's suites furniture.
The fit-out work for all the F&B outlets is ongoing.
Progress Updates
Nakheel’s building completion certificate (BCC) has been obtained.
Trakhees’s BCC is expected to be issued in February 2020.
The furniture supplier has manufactured 70% of the guest's suites furniture.
The fit-out work for all the F&B outlets is ongoing.
The testing and commissioning of the HVAC system will commence in February 2020.
Progress Updates
Trakhees's building completion certificate (BCC) has been obtained.
The furniture supplier has manufactured 85% of the Guest's suites furniture.
The fit-out work for all the F&B outlets is ongoing, where 60% of the work has been completed already.
The testing and commissioning of the HVAC system have commenced.
Progress Updates
The furniture supplier has manufactured the full quantity of the Guest's suites furniture, and he will commence with the delivery and installation of the furniture in April 2020.
The fit-out work for all the F&B outlets is ongoing, where 70% of the work has been completed already.
30% of the testing and commissioning of the HVAC system has been completed.
Progress Updates
The delivery of the furniture is in progress.
The fit-out work for all the F&B outlets is ongoing, where 80% of the work has been completed already.
The delivery and installation of commercial kitchens are in progress.
70% of the testing and commissioning of the HVAC system has been completed. The end of June 2020 is the target completion date of this activity.
Progress Updates
The delivery of the furniture is in progress.
The fit-out work for all the F&B outlets is ongoing, where 93% of the work is complete.
The installation of the commercial kitchens is in progress.
The snagging process is due to complete by the end of August 2020.
Progress Updates
The delivery and installation of the furniture are in progress.
The fit-out work for all the F&B outlets is complete. Snagging work is in progress.
The installation of the commercial kitchens is 80% complete.
The de snagging process is complete.
Progress Updates
The delivery and installation of the furniture are 70% complete.
The snagging of the fit-out work for all the F&B outlets is complete.
The installation of the commercial kitchens is 90% complete.
Progress Updates
The delivery and installation of the furniture are complete.
The snagging of the furniture has commenced.
The installation of the commercial kitchens is 100% complete.
The fit-out final de snagging for the F&B (food and beverage outlets) is underway.
The delivery of the OSE (Operation supplies and equipment) has commenced.
Progress Updates
The fit-out final de snagging for the F&B (food and beverage outlets) is 70% complete.
The furniture for all the F&B outlets has been ordered.
Work has commenced at the swimming pool barbeque area and the restaurant's terrace.
The delivery of the OSE (Operation supplies and equipment) is 75% complete.
Progress Updates
The fit-out final de snagging for the F&B (food and beverage outlets) is complete.
70% of the furniture for all the F&B outlets has been produced.
50% of the work at the swimming pool barbeque area and the restaurant's terrace is complete.
The delivery of the OSE (Operation supplies and equipment) is 90% complete.
The handing over process of the hotel to the operation team has commenced.
Progress Updates
The furniture for all the F&B outlets has been delivered and installed.
The work at the swimming pool barbeque area and the restaurant's terrace is complete.
The delivery of the OSE (Operation supplies and equipment) is complete.
The handing over process of the hotel to the operation team will be completed on September 2021.
Progress Updates
The hotel is open and operational.
Progress Updates
Construction Completed