Mises à jour sur les progrès
The snagging/ de snagging process of the units has started and expected to be completed by the end of June, 2013.
The temporary power required for carrying out the AC testing and commissioning should be supplied to the building by the authorities in the middle of July 2013; the contractor will need 3 weeks to complete this task.
Once the above task is completed the final coat of paint will be applied and then the delivery of the furniture will follow; this process should be starting at the end of August, 2013 and it needs 45 days to be completed; in the interim the civil defense and Dubai municipality certificates will be obtained and collected.
75% of the units have been de snagged; the balance will be completed by the end of July 2013.
The fixing of the kitchen cabinets in all the units will be completed by the end of July, 2013.
The steel Mesh at the top of the building’s façade will be completed by the first week of August, 2013.
20% of the furniture has been manufactured by the supplier.
The civil defense (CD) first inspection is expected to take a place during the second week of August, 2013; Dubai municipality (DM) inspection should follow once the CD certificate is issued; this should be in early September, 2013.
85% of the unitshave been de snagged; the balance will be completed by the end of August 2013.
The fixing of the kitchen cabinets in all the units will be completed by the end of August, 2013.
The steel Mesh at the top of the building’s façade will be completed by end of August, 2013.
40% of the furniture has been manufactured by the supplier.
The civil defense (CD) first inspection is expected to take a place during the second week of September, 2013; Dubai municipality (DM) inspection should follow once the CD certificate is issued; this should be in late September or early October, 2013.
All the units have been de-snagged.
The installation of the kitchen cabinets in all the units has been completed.
The steel Mesh at the top of the building’s façade will be completed by middle the of October, 2013. The shipment from Italy was delayed by the manufacturer for reasons beyond our control.
60% of the furniture has been manufactured by the supplier with the balance due to be completed very shortly.
The civil defense (CD) first inspection is expected to take a place during the second week of October, 2013; this inspection was pushed back from its originally planned time because there has been a delay in getting the permanent power from Dubai electricity and water authority (DEWA); Dubai municipality (DM) inspection should follow once the CD certificate is issued; this should be in middle of November, 2013.
Mises à jour sur les progrès
All the units have been de-snagged.
The installation of the kitchen cabinets in all the units has been completed.
The steel Mesh at the top of the building’s façade will be completed by middle the of October, 2013. The shipment from Italy was delayed by the manufacturer for reasons beyond our control.
60% of the furniture has been manufactured by the supplier with the balance due to be completed very shortly.
The civil defense (CD) first inspection is expected to take a place during the second week of October, 2013; this inspection was pushed back from its originally planned time because there has been a delay in getting the permanent power from Dubai electricity and water authority (DEWA); Dubai municipality (DM) inspection should follow once the CD certificate is issued; this should be in middle of November, 2013.
The installation of the steel Mesh feature at the top of the building’s façade has commenced; it will be completed by second week of November, 2013.
75% of the furniture has been manufactured by the supplier with the balance due to be completed very shortly.
The civil defense (CD) first inspection is expected to take a place during the third week of November, 2013; this inspection was pushed back from its originally planned time because there has been a delay in getting the permanent power from Dubai electricity and water authority (DEWA); Dubai municipality (DM) inspection should follow once the CD certificate is issued; this should be in middle of December, 2013.
The installation of the steel Mesh feature at the top of the building’s façade and the car parking podiums has commenced; the front elevation is completed; the remaining sides will be completed by the first week of December, 2013.
The final paint coat inside the units has been done; the corridors final coat will be done after getting all the furniture installed in the units.
80% of the furniture has been manufactured by the supplier with the balance due to be completed by the middle of Dec, 2013. One tower crane has already been removed and once the steel Mesh installation is completed the second one will be dismantled.
Civil defense (CD) inspection is scheduled to take a place during the second week of December, 2013.
Dubai Municipality inspection is expected to take a place by the end of December 2013; DM certificate will be issued thereafter.
The installation of the steel Mesh feature at the top of the building’s façade and the car parking podiums has been completed.
The final paint coat inside the units has been done; the corridors final coat will be done after getting all the furniture installed in the units.
The delivery of the furniture by the supplier has commenced with the full building furnishing due to be completed by the end of January, 2014.
The second tower crane has already been removed.
Civil defense (CD) inspection is scheduled to take a place during the first week of January, 2014.
Dubai Municipality inspection is expected to take a place by the end of January 2014; DM certificate will be issued thereafter.
Mises à jour sur les progrès
The installation of the steel Mesh feature at the top of the building’s façade and the car parking podiums has been completed.
The second crane has been removed.
The final paint coat inside the units has been done; the corridors final coat will be done after getting all the furniture installed in the units.
The delivery of the furniture by the supplier has commenced with the full building furnishing due to be completed by the end of the middle of March, 2014.
Civil defense (CD) had their first inspection to the building on 19/1/2014. A list of comments was issued to the contractors; they are working through it and need 3 weeks to complete it.
Once the CD certificate is issued Dubai Municipality inspection will follow which is expected to take a place by the end of Feb 2014; DM certificate will be issued thereafter.
The delivery of the furniture by the supplier has commenced with the full building furnishing due to be completed by the middle of March, 2014.
Civil defense certificate issued on 19/2/2014.
Dubai Municipality first inspection was carried out on 24/2/2014, minor comments were issued; the next inspection is scheduled on 3/3/2014; DM certificate will be issued thereafter.
Dubai Municipality completion certificate was issued on 26/05/2014.
The building was fully energized on the 4th of May, 2014.
The contractor has completed the testing and commissioning of the Air Conditioning systems in the building.
The furniture delivery has commenced with installation due to be completed by the end of July, 2014.
The corridors final coat of paint will be completed after all the furniture is installed in the units.