Progress Updates
April 2024 - May 2024 Updates:
MEP work throughout the building is 95% complete.
The installation of the building’s external curtain wall is 99% complete.
The installation of the conveying system is 97% complete.
Installation of the guestroom shower glass is complete.
Guestroom door installations are complete.
The lift lobby glass partition and floor finishes are 98% complete.
The landscaping, fountain area, and swimming pool are 70% complete.
The First Group’s project team is finalising the appointment of the building façade lighting specialist.
DCD has approved the breaching inlet inspection, and a certificate was issued.
DEWA team is conducting workshops to complete the HV cable pulling and substation energising.
The RTA consultant obtained the NOC for the external paving design, and the specialist subcontractor applied for the construction NOC.
The First Group’s interior design team is conducting workshops with the F&B team and kitchen consultant to develop the design for the all-day dining area at levels 13 and 14.
The First Group’s interior design team is working on the detailed designs for the main lobby, prayer room, and public bathroom at levels 01, 11, and 76.
The First Group’s interior design team is working on the detailed designs for the typical guest corridor and lift lobby.
Progress Updates
April 2024 - May 2024 Updates:
MEP work throughout the building is 95% complete.
The installation of the building’s external curtain wall is 99% complete.
The installation of the conveying system is 97% complete.
Installation of the guestroom shower glass is complete.
Guestroom door installations are complete.
The lift lobby glass partition and floor finishes are 98% complete.
The landscaping, fountain area, and swimming pool are 70% complete.
The First Group’s project team is finalising the appointment of the building façade lighting specialist.
DCD has approved the breaching inlet inspection, and a certificate was issued.
DEWA team is conducting workshops to complete the HV cable pulling and substation energising.
The RTA consultant obtained the NOC for the external paving design, and the specialist subcontractor applied for the construction NOC.
The First Group’s interior design team is conducting workshops with the F&B team and kitchen consultant to develop the design for the all-day dining area at levels 13 and 14.
The First Group’s interior design team is working on the detailed designs for the main lobby, prayer room, and public bathroom at levels 01, 11, and 76.
The First Group’s interior design team is working on the detailed designs for the typical guest corridor and lift lobby.
Progress Updates
June - July 2024 Updates:
The project consultant and contractor have submitted the BCC application and are currently attending to all comments before re-inspection.
MEP activities for T&C and balancing are ongoing, alongside addressing BCC comments on the building.
Curtain wall installation is completed, and specialists are replacing damaged and broken panels.
The convey system installation is completed, and authority comments are being attended to.
Lift lobby glass partition and floor finishes have reached 100% completion.
Fountain and swimming pool work are 85% complete as part of the landscape project.
The First Group has appointed the building's façade light supplier.
The DEWA substation has been energized, and the building is now supplied with power.
The external paving contractor has obtained the construction NOC, and work has commenced on-site.
The guest room furniture contractor has been appointed.
The guest room decorative lights package has been selected, and the order is being processed.
Continuous workshops involving the project consultant, contractor, and specialists are ongoing to resolve infrastructure service clashes with the building's service road.
The First Group's interior team is in continuous workshops with F&B and kitchen consultants to develop the design for the all-day dining on levels 13 and 14.
The First Group's interior team has completed the main lobby design, which is under review by all stakeholders.
The First Group's interior team has completed enhancement designs for the typical corridors.
The First Group's interior and project teams are in continuous workshops with the hotel operator and F&B team to develop the drop area and leisure deck design on level 11.
Progress Updates
June - July 2024 Updates:
The project consultant and contractor have submitted the BCC application and are currently attending to all comments before re-inspection.
MEP activities for T&C and balancing are ongoing, alongside addressing BCC comments on the building.
Curtain wall installation is completed, and specialists are replacing damaged and broken panels.
The convey system installation is completed, and authority comments are being attended to.
Lift lobby glass partition and floor finishes have reached 100% completion.
Fountain and swimming pool work are 85% complete as part of the landscape project.
The First Group has appointed the building's façade light supplier.
The DEWA substation has been energized, and the building is now supplied with power.
The external paving contractor has obtained the construction NOC, and work has commenced on-site.
The guest room furniture contractor has been appointed.
The guest room decorative lights package has been selected, and the order is being processed.
Continuous workshops involving the project consultant, contractor, and specialists are ongoing to resolve infrastructure service clashes with the building's service road.
The First Group's interior team is in continuous workshops with F&B and kitchen consultants to develop the design for the all-day dining on levels 13 and 14.
The First Group's interior team has completed the main lobby design, which is under review by all stakeholders.
The First Group's interior team has completed enhancement designs for the typical corridors.
The First Group's interior and project teams are in continuous workshops with the hotel operator and F&B team to develop the drop area and leisure deck design on level 11.
Progress Updates
August - September 2024 Updates:
The project consultant and contractor have submitted the BCC application and are in the final stage of obtaining the certificate.
MEP activities for T&C and balancing are ongoing.
Curtain wall installation is complete, and specialists are replacing damaged panels.
The conveyor system installation is complete.
Hardscape project fountain and swimming pool work are complete.
External paving and project entry/exit work are complete.
The guest room furniture contractor is on-site conducting surveys and material procurement.
External infrastructure clashes have been resolved, with specialist contractors competing for the job.
Ongoing workshops between The First Group's team and the hotel operator address outstanding comments.
Ongoing workshops between The First Group's interior team, F&B consultants, and kitchen consultants are developing the design for the All-Day Dining on levels 13 and 14.
The First Group's interior team has completed the main lobby design and presented it for tendering.
Enhancement design for typical corridors has been completed by The First Group's interior team.
Ongoing workshops between The First Group's interior and project teams, the hotel operator, and the F&B team are developing the drop area and leisure deck design on level 11.
Progress Updates
August - September 2024 Updates:
The project consultant and contractor have submitted the BCC application and are in the final stage of obtaining the certificate.
MEP activities for T&C and balancing are ongoing.
Curtain wall installation is complete, and specialists are replacing damaged panels.
The conveyor system installation is complete.
Hardscape project fountain and swimming pool work are complete.
External paving and project entry/exit work are complete.
The guest room furniture contractor is on-site conducting surveys and material procurement.
External infrastructure clashes have been resolved, with specialist contractors competing for the job.
Ongoing workshops between The First Group's team and the hotel operator address outstanding comments.
Ongoing workshops between The First Group's interior team, F&B consultants, and kitchen consultants are developing the design for the All-Day Dining on levels 13 and 14.
The First Group's interior team has completed the main lobby design and presented it for tendering.
Enhancement design for typical corridors has been completed by The First Group's interior team.
Ongoing workshops between The First Group's interior and project teams, the hotel operator, and the F&B team are developing the drop area and leisure deck design on level 11.