Millennium Place Marina
With its breathtaking views across Dubai Marina and central location close to the district’s many attractions, Millennium Place Marina is a jewel in The First Group's crown. The hotel boasts 462 luxury guestrooms and suites, landmark dining options and a comprehensive array of guest amenities and leisure facilities, making it the perfect home-away-from-home for business and leisure guests.
Millennium Place Marina is located within walking distance of the Marina’s major attractions including Marina Mall, The Walk – with its appealing streetside cafes and restaurants – and Bluewaters Island, which is home to the world’s biggest observation wheel, Ain Dubai. It is also conveniently located close to major transportation links including the Dubai Metro and Dubai Tram. These factors perfectly position Millennium Place Marina Marina as one of the Marina’s most popular hotels.
PREMIUM LOCATION
Within walking distance of major attractions
GUEST CONVENIENCES
Including integrated retail outlets
A BIRD'S EYE VIEW OF MILLENNIUM PLACE MARINA, DUBAI MARINA'S STUNNING LOCATION
Millennium Place Marina is located in the heart of Dubai Marina, close to the precinct's many attractions.
FACILITIES
24-hour Reception
24/7 reception and concierge services
Valet Parking
Complimentary valet parking service
Business Lounge
Modern, high-tech facilities for business guests
Laundry service
24/7 laundry service
Wi-Fi
Complimentary high-speed internet access
World-class Dining Facilities
A fine selection of restaurants, cafes and bars
Swimming pool
Stunning rooftop swimming pool and sundeck
Gymnasium
Fully-equipped fitness centre
Satellite Television
Local and international digital channels
Booking Facilities
Tour and leisure activity booking services
Gallery
Project Development Progress
Progress Updates
The preliminary design drawings have been approved by Dubai Municipality.
Prior to the above submittal other approvals on the design of the hotel had been obtained from the relevant authorities such as Dubai Electricity and Water Authority (DEWA), Dubai civil defence, Dubai Tourism and Commerce Marketing (DTCM), Etisalat, the Road and Transport Authority (RTA) and the master developer.
The enabling works (shoring & piling) have been awarded; the appointed contractor has submitted his design drawings to the relevant authorities to obtain the building permit. Once the permit is issued he will immediately start the mobilization of his equipment to the site and the commencement of the enabling works will begin.
The hotel operator is heavily involved with the project architect and our in house design team at this design stage to ensure that the operational requirements are met. This involvement will cover almost all of the hotel spaces and relevant operational aspects ensuring a construction process that is unhindered by delays occasioned by on-going design changes.
Progress Updates
The shoring and piling contractor has completed his mobilization at the site.
The shoring and piling contractor has commenced works at the site.
Standard room’s concept design is still under review by the operator.
VIP’s suite design was completed on 28/5/2015 and has been sent to the operator for their review and feedback.
VIP lounge was completed on 28/5/2015 and has been sent to the operator for their review and feedback.
Architectural layouts in some areas have been revised slightly based on the operator recommendation to enable better circulation.
Progress Updates
The shoring and piling contractor has commenced with the works.
85% of the shoring piles are completed.
18% of the construction piles are completed.
Standard room’s concept design has been approved by the operator.
The First Group interior design team is working on modifying the design of the VIP suites based on the comments received from the operator.
The First Group interior design team is working on modifying the design of VIP lounge based on the comments received from the operator.
Architectural layouts in some areas have been revised slightly based on the operator recommendation to enable better circulation.
The consultant has submitted the final design drawings of the hotel to relevant authorities in order to obtain the necessary approvals.
Progress Updates
The shoring and piling contractor has commenced with the works.
The shoring piles are completed.
35% of the construction piles are completed.
The final design drawings of the hotel have been approved by the relevant authorities.
Standard room’s concept design has been approved by the operator.
The First Group interior design team has modified the design of the VIP suites based on the comments received from the operator and reissued it to the operator for their final review and approval.
The First Group interior design team has modified the design of VIP lounge based on the comments received from the operator and reissued it to the operator for their final review and approval.
Progress Updates
The shoring and piling work has been completed.
All the piles have been tested and approved as per the authorities’ regulations.
The shoring and piling contractor is carrying out the minor excavation work which is required. Expected to be completed on the 10th of September, 2015
The main contractor will be formally appointed during the 1st week of September, 2015 so that they can collect the main building permit from the authorities and commence with their work.
The First Group interior design team has issued the operator approved standard room’s concept design drawings to the project’s architect.
The operator has approved the modified designs of the VIP lounge and suites which were presented by The First Group interior design team.
The First Group interior design team is working on the design of the lobby and the F&B outlets.
Progress Updates
The shoring and piling work has been completed.
All the piles have been tested and approved as per the authorities’ regulations.
The shoring and piling contractor is carrying out the minor excavation work which is required. Expected to be completed on the 10th of September, 2015
Al Habbai contracting has been appointed as the main contractor of the project.
The building permit should be issued during the first week of October, 2015.
The contractor will commence with the mobilization to the site once the building permit and the construction NOC (No Objection Certificate) are issued by the relevant authorities; this is expected to occur around the 15th of October, 2015.
The operator has approved the modified designs of the VIP lounge and suites which were presented by The First Group interior design team. As a result of this approval The First Group interior design team is currently preparing the detailed design drawings for these approved areas.
The First Group interior design team has completed the design of the lobby and still working on the design of the F&B outlets.
Progress Updates
The main building permit and the main construction No Objection Certificate have been issued on 20/10/2015.
Al Habbai Contracting, the main contractor of the project has completed his mobilization to the site and has commenced with the main building work.
The First Group interior design team is currently preparing the detailed design drawings for all the common areas and the hotel rooms based on the operator approval of the concept design for those areas.
The First Group interior design team has sent the initial concept design drawings for the Food and Beverages outlets to the operator for their review and comments.
Progress Updates
The main building permit and the main construction No Objection Certificate have been issued on 20/10/2015.
Al Habbai Contracting, the main contractor of the project has commenced with the following work: Piles’ cutting, Casting and fixing of the Shoring panels, Excavation as part of the raft foundation preparation.
The casting of the raft foundation slab is planned to be on the 20th of Dec, 2015.
The First Group interior design team has prepared the detailed design drawings for the hotel rooms and forwarded the same to the project’s consultant as part of the final interior design package. The team is still working on the design drawings of the common areas and the rest of the F and B outlets based on the comments received from the operator.
Main lobby design is under progress.
BOH layout has been revised to meet the operator’s standards and requirements. Accordingly the same has been shared with the consultant so they can work on the revision of the drawings.
Progress Updates
Al Habbai Contracting, the main contractor of the project has completed his mobilization to the site.
The contractor has poured the concrete for the first part of the raft foundation. The second and the final part of the foundation will be poured around the 14th of Jan, 2016.
The First Group interior design team is still incorporating the designs of the common areas, main lobby and the rest of the F and B outlets based on the comments received from the operator. Workshop sessions between our interior design team and the operator team are ongoing for this regard.
BOH layout has been revised to meet the operator’s standards and requirements. Accordingly the consultant has resubmitted the new layout drawings for the authorities for their review and approval. Approval has been obtained.
Progress Updates
The contractor has poured the concrete for the raft foundation.
The casting of the ground floor slab is planned for the 17th of Feb, 2016.
The First Group interior design team will be presenting the designs of the common areas, main lobby and the rest of the F and B outlets based on the suggestions received from the operator by the middle of February, 2016.
Progress Updates
The contractor has poured the concrete for the ground floor slab.
The casting of the first floor slab is planned for the 17th of March, 2016.
The First Group interior design team has presented the designs of the common areas, main lobby and the rest of the F and B outlets to the operator based on his suggestions for his review and approval.
All rooms’ layouts have been issued to the main contractor for execution.
Mock up room to be prepared on site as part of the operator’s samples and finishes approvals purpose.
Rooms’ designs (Standard and VIP) will be presented to the operator in the coming two weeks.
The Main Lobby concept design is under progress and it will be ready for the operator’s review by Middle of April, 2016.
Progress Updates
The contractor has poured the concrete for the 2nd floor slab.
The casting of the 3rd floor slab is planned for the 10th of April, 2016.
The First Group interior design team has presented the designs of the common areas, main lobby and the rest of the Food and Beverage outlets to the operator; minor comments were received and The First Group Interior Design team is working to incorporate those comments in the final design.
Mock up room to be prepared on site as part of the operator’s samples and finishes approvals process.
Rooms’ designs (Standard and VIP) have been presented to the operator; we are waiting for their feedback.
The Main Lobby concept design is under progress and it will be ready for the operator’s review by the middle of April, 2016.
Progress Updates
The contractor has poured the concrete for the 5th floor slab.
The casting of the 6th floor slab is planned for the 5th of May, 2016.
The First Group interior design team has incorporated the operator’s comments into the designs of the common areas, main lobby and the rest of the Food and Beverage outlets and reissued the design drawings for the operator final review and sign off.
Rooms’ designs (Standard and VIP) have been approved by the operator.
The selection of the sanitary ware, mixers, wall and floor tiles to be used in the hotel’s rooms has been finalized and approved by the operator.
The Mock up room will be prepared on site as part of the operator’s samples and finishes approvals process.
Progress Updates
The contractor has poured the concrete for the 9th floor slab.
The casting of the 10th floor slab is planned for the 6th of June, 2016.
All rooms’ layouts, BOH, MEP and commercial kitchen drawings have been approved by the operator and were issued to the main contractor for execution.
Rooms’ designs (Standard and VIP) have been approved by the operator.
The Main Lobby concept design has been shared with the operator; the interior design team is working on the comments received.
Spa initial layout has been approved by the operator.
Progress Updates
The contractor has poured the concrete for the 12th floor slab.
The casting of the 13th floor slab is planned for the 4th of July, 2016.
The Main Lobby concept design has been approved by the operator.
Spa initial layout has been approved by the operator.
Progress Updates
The contractor has poured the concrete for the 15th floor slab.
The casting of the 16th floor slab is planned for the 7th of August, 2016.
The First Group interior design team is preparing the required detailed design drawings for the Main Lobby and the SPA as per the operator’s approved concept design.
The First Group interior design team is developing the designs for the hotel’s food and beverage outlets for the operator’s final review and approval.
Progress Updates
The 19th floor slab was completed on 26/08/2016.
The 20th floor slab concrete pouring expected to be on 4/09/2016.
The topping out of the building is expected to be before the end of September, 2016. The block work is completed up to the 11th floor. The work is ongoing in the 12th, 13th and the 14th.
The façade curtian wall work will commence by the end of September, 2016.
The mock up room will be ready by the 8th of September, 2016 for the operator review and final approval.
Spa layout and mood images which have been prepared by The First Group design team have been approved by the operator, final design with 3Ds to be issued on October.
The final Main lobby architectural/interior layouts are ready and will be shared with the operator for their final review and sign off.
Initial site mock up for the proposed corridor design to be prepared for our review and approval.
Progress Updates
The block work is completed up to the 13th floor. The work is ongoing in the 14th, 15th and the 16th.
The façade curtain wall samples are under installation.
The mock up room has been completed and inspected by the operator. Minor comments were raised during the inspection. The First Group interior designer team is attending to these comments.
The final Main lobby architectural/interior layouts have been shared with the operator for their final review and sign off.
Initial site mock up for the proposed corridor design is under preparation for our review and approval.
Progress Updates
The block work is completed up to the 15th floor. The work is ongoing in the 16th and the 17th.
The façade curtain wall samples have been approved and the fabrication of the same is under way.
The mock up room has been approved by the operator.
Minor comments were received from the operator on the final Main lobby architectural/interior layouts. The First Group’s Interior design team is attending to these comments.
Initial site mock up for the proposed corridor design is under preparation for our review and approval.
Progress Updates
Block works completed up to 18th floor.
Block work is going on for 19th & 20th floors.
Plaster works for 10th floor completed and in progress on the 11th &12th floors.
Bathrooms wall tiles work is going on in 9th floor.
Floor tile work is going on in 2nd and 3rd floors.
Paint work for primer and stucco is going on from the first to ninth floors.
All Lifts-9 nos. delivered at site & installation commenced on 20th November.
The First Group’s Interior design team has incorporated all the design comments which were received from the operator for the main lobby and all day dining restaurant.
The site mock up for the proposed corridor design has been prepared and viewed by The First Group’s Interior design team; waiting for the operator’s review and comments if any.
Progress Updates
Block works completed up to 21st floor and is in progress on the 22nd floor.
Plaster work is completed up to 17th floor and is in progress on the 18th floor
Paint works are in progress up to 12th floor.
Floor tiles completed up to 6th floor.
Wall tiles works are completed up to 15th floor.
50% of the doors and frames on the hotel 9 lifts has been completed.
Design Progress: The First Group’s Interior design team is working on getting the final designs of the main lobby and all day dining restaurant ready for the operator’s final review and approval.
Design Progress: The site mock up for the proposed corridor design has been viewed by the operator; a few comments were highlighted. The First Group Interior design team is attending to those comments.
Progress Updates
Block works completed up to 22nd floor and in progress on the roof floor.
Plaster work completed up to 19th floor and in progress on the 20th floor
Paint works are in progress up to 14th floor.
Floor tiles are completed up to 7th floor and are in progress on the 8th floor.
Wall tiles works are completed up to 16th floor and are in progress on the 17th.
60% of the doors and frames for the hotel 9 lifts have been completed.
The First Group’s Interior design team has completed the final designs of the main lobby and the ground floor restaurant. The designs have been sent for the operator’s review and approval.
The site mock up for the proposed corridor design has been approved by the operator.
Progress Updates
Plaster work completed up to 20th floor and in progress on the 21st floor
Paint works are in progress up to 16th floor.
Floor tiles are completed up to 8th floor and are in progress on the 9th floor.
Wall tiles works are completed up to 18th floor and are in progress on the 19th.
70% of the doors and frames for the hotel’s 9 lifts have been completed.
The final designs of the main lobby and VIP Lounge has been reviewed by the operator; a few comments were highlighted. The First Group interior design team is working on these comments.
Based on the workshop session that The First Group interior design team had with the operator, The First Group interior design team has issued the design drawings of the ground floor restaurant to the operator for their review and feedback.
Progress Updates
Plaster work completed up to 21st floor and in progress on the 22nd floor
Paint works are in progress up to 18th floor.
Floor tiles are completed up to 10th floor and are in progress on the 11th and 12th floors.
Wall tiles works are completed up to 19th floor and are in progress on the 20th.
80% of the doors and frames for the hotel’s 9 lifts have been completed.
The final designs of the main lobby and VIP Lounge have been approved by the operator.
The workshop sessions between The First Group interior design team and the operator are ongoing for the finalization of the ground and first floors restaurants designs.
Progress Updates
Plaster work has been completed in all the floors.
Paint works are in progress up to 21st floor.
Floor tiles are completed up to 16th floor and are in progress on the 17th floors.
Wall tiles works are completed up to 20th floor and are in progress on the 21st.
90% of the doors and frames for the hotel’s 9 lifts have been completed.
The contractor will commence with the main lobby works shortly based on the approved design drawings.
The concept designs of the ground and first floor restaurants have been finalized and approved by the operator. The First Group interior design team is preparing the detailed drawings for the same outlets.
Progress Updates
Plaster work has been completed on all of the floors.
Paint works are in progress up to the 22nd floor.
Floor tiles are completed up to 17th floor and are in progress on the 18th floor.
Wall tiles works are completed up to 21st floor and are in progress on the 22nd floor
90% of the doors and frames for the hotel’s 9 lifts have been completed.
The contractor has commenced with the main lobby works.
The First Group interior design team has completed the required drawings for the ground floor restaurant and are working on the First floor restaurant.
Progress Updates
Floor tiles are completed up to 19th floor and are in progress on the 20th floor.
Wall tiles works are completed are in progress on the 22nd floor.
95% of the doors and frames for the hotel’s 9 lifts have been completed.
The First Group interior design team has completed the design works for the First floor restaurant. The required drawings needed for tendering are under preparation by the team.
The First Group design team has floated the tender of the ground floor restaurant to four fit out contractors. We are expecting to receive the quotes by the end of July, 2017.
The First Group interior design team is preparing the furniture tender package.
Progress Updates
Floor tiles are completed up to 20th floor and are in progress on the 21st floor.
Wall tiles works are completed are in progress on the 22nd floor.
95% of the doors and frames for the hotel’s 9 lifts have been completed.
The First Group interior design team has completed the design works for the first floor restaurant. The required drawings needed for tendering are under preparation by the team.
The First Group design team has received the quotes for the ground floor restaurant from the participating contractors. The quotes are under evaluation by our interior design team.
The First Group interior design team has floated the furniture tender package for the short listed suppliers. Expected to receive the quotes by the end of August 2017.
Progress Updates
Floor tiles are completed up to 21st floor and are in progress on the 22nd floor.
Wall tiles works are completed up to 21st floor and are in progress on the 22nd floor.
95% of the doors and frames for the hotel’s 9 lifts have been completed.
The First Group interior design team has prepared the design drawings for the first floor restaurant which are needed for tendering of the fit out work.
The First Group design team is still reviewing the received quotes for the ground floor restaurant from the participating fit out contractors. Several workshop sessions took place with all bidders in order to ensure that we select the right contractor for the job.
The furniture tender package quotes have been received and they are under evaluation by The First Group Interior design team.
Progress Updates
Floor tiles are completed up to 22nd floor and are in progress at the roof top level.
Wall tiles works are completed up to 22nd floor; minor snags work is in progress.
The Fit out work contractor for the ground floor restaurant and lobby area has been appointed. His mobilization to the site will commence during the 1st week of October, 2017.
The furniture package has been awarded.
Progress Updates
Floor tiles are completed, snagging work is in progress.
Wall tiles works are completed up to 22nd floor; minor snags work is in progress.
The Fit out work contractor for the ground floor restaurant and lobby area has completed hiss mobilization to the site.
The preparation of the fit out work has commenced including the materials submittal and approval process.
15% of the guestroom’s furniture has already been manufactured
Progress Updates
The Fit out works for the ground floor restaurant and the lobby areas are in progress.
45% of the guestroom’s furniture has already been manufactured
Progress Updates
The contractor has completed all the civil works and working towards getting Civil Defence inspection scheduled for the 15th of Jan, 2018.
Dubai Municipality completion certificate is expected to be issued by 10th of Feb, 2018.
The de snagging work is ongoing in all areas of the hotel
Fit-out contractors are working on the ground floor lobby, restaurants and common areas.
The Furniture Company has produced 75% of the required furniture and 50% of it has already been delivered to the site.
Progress Updates
Civil Defence has completed their first inspection. A few comments were highlighted and the contractor is working on dealing with them.
Dubai Municipality completion certificate is expected to be issued by the end of Feb, 2018.
Fit-out contractors are working on the ground floor lobby, restaurants and common areas.
The Furniture Company has produced 85% of the required furniture and 50% of it has already been delivered to the site.
Progress Updates
All Civil Defence comments are completed by the contractor. The second inspection for the Civil Defence is confirmed for the 4th of March, 2018.
Dubai Municipality completion certificate is expected to be issued by the second week of March, 2018.
The first phases of the ground floor lobby, restaurants and common areas have all been completed.
The Furniture Company has produced 90% of the required furniture and 60% of it has already been delivered to the site.
Progress Updates
The Civil Defence Completion certificate has been issued.
Dubai Municipality completion certificate is expected to be issued by the second week of April, 2018.
The fit out work for the common areas, lobby and F&B outlets is ongoing.
The furniture supplier has produced 100% of the required furniture and 75% of it has already been delivered to the site.
Progress Updates
The Civil Defence Completion certificate has been issued.
Dubai Municipality has carried out the first inspection and provided some minor comments for the contractor to complete before they can issue their completion certificate. The contractor is attending to these comments.
The fit out work for the common areas, lobby and F&B outlets is ongoing.
The furniture supplier has produced 100% of the required furniture and 85% of it has already been delivered to the site.
Progress Updates
The building completion certificate has been issued by Dubai Municipality.
50% of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The furniture supplier has produced 100% of the required furniture and 95% of it has already been delivered to the site.
The furniture supplier has already commenced with the installation of the furniture.
Progress Updates
65% of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The furniture supplier has delivered 100% of the required furniture and 35% of it has already been installed.
Progress Updates
75% of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The furniture supplier has delivered 100% of the required furniture and the majority of it has already been installed.
Progress Updates
Guest rooms have all been furnished.
80% of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The furniture supplier for the common and F&B areas has commenced with the production and fabrication of the remaining required furniture.
Progress Updates
All guest rooms have been fully furnished.
85% of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The furniture samples for the common and F&B areas are under preparation and should be ready by next week.
Progress Updates
93% of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The furniture samples for the common and F&B areas have been manufactured and viewed by the Interior Designer.
Progress Updates
95% of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The furniture for the common and F&B areas will be delivered and installed by the end of December 2018.
Progress Updates
95% of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The furniture for the common and F&B areas will be delivered and installed by the end of January 2018.
Progress Updates
The de-snagging of the fit-out work for the common areas, lobby and F&B outlets has been completed.
The delivery and installation of the furniture for the common and F&B areas has been completed.
All the comments which were highlighted during the first inspection by Dubai Department of Tourism and Commerce Marketing (DTCM) of the hotel have been completed. The second inspection is scheduled for the 12th of March 2019.
The handing over process of the hotel’s guest rooms and common areas to the operator has commenced.
Progress Updates
The Department of Tourism and Commerce Marketing (DTCM) in Dubai have completed their second inspection of the hotel. They are expected to issue their final approval for opening the hotel around the 15th of April 2019.
The handing over process of the hotel’s guest rooms and common areas to the operator has been completed.
The launch event for MasterChef, the TV Experience, a world first dining concept based upon and powered by the global phenomenon that is MasterChef, will take a place on the 17th of April 2017.
WHY OWN IN DUBAI MARINA?
As one of Dubai’s most popular tourist precincts, Dubai Marina’s hotel sector ranks among the emirate’s best-performing markets, making it a prime target for savvy owners.